What Bellaire's $6.50 Stormwater Fee Pays Toward
The monthly fee is one small piece of a much larger drainage-finance picture.

Every residential parcel in Bellaire pays a flat stormwater fee of $6.50 a month in fiscal year 2026, which ran from October 1, 2025, through September 30, 2026. That comes to $78 a year. The fee sits on the City's utility rate sheet, on the same bill as water, sewer and trash.
Fiscal year 2027 began on October 1, 2026. The City publishes a new rate sheet each year, and I could not confirm the FY2027 stormwater figure, so $6.50 is the last rate I can document. Check the current sheet on the City's website before you quote it.
The fee is one piece of a larger drainage picture. Voters approved a $40 million drainage bond in 2024, the City budgeted $8.35 million for its regional drainage program in FY2026, and a $54 million grant row sits in the same budget. Here are the dates, the amounts and what the City's sources do and do not say about where the money goes.
The short version
- The City Council established a municipal drainage utility on August 5, 2024.
- The Council adopted stormwater utility fees on September 16, 2024, for FY2025.
- The FY2026 residential stormwater fee is a flat $6.50 per month per parcel, effective October 1, 2025.
- Proposition A, which passed on November 5, 2024, authorized $40 million for drainage facilities and improvements.
- The FY2026 adopted budget includes $8.35 million for the Regional Drainage Program, project DR2202.
- The same budget lists $54 million for the Cypress Ditch Regional Flood Mitigation Project, a grant-funded row.
How the fee began
The City says its Council established a municipal drainage utility system on August 5, 2024. About six weeks later, on September 16, 2024, the Council adopted the stormwater utility fees. The City says that was for implementation in FY2025.
The stormwater fee appears on the City's utility rate sheet with the rest of the monthly charges. It is a flat amount per parcel. A small bungalow and a big new build on the same size lot pay the same line.
What $6.50 looks like on a bill
The FY2026 rate sheet lists the residential stormwater fee as a flat $6.50 per month per parcel. Other fixed charges on the same sheet, effective October 1, 2025, include a small-meter water charge of $13.19 a month and a base sewer charge of $12.43 a month. The residential solid waste total, which covers sanitation and recycling, is $31.19 a month.
Add those four fixed amounts and you get $63.31 a month before any water or sewer use is billed. That is a sum of the posted figures, not a total that appears on the City's sheet, and it assumes a small meter. Your own bill depends on your meter and your use. In plain terms, the stormwater line is about a tenth of the fixed part of a typical monthly bill.
What the sources say the money is for
The City's pages set the rate. They do not break the $6.50 down into line items, and they do not say how many dollars a year the fee raises in total. So I will not tell you the fee pays for any one project.
What the sources do show is a set of drainage commitments that sit alongside the fee: - A $40 million bond authorization. The City says Proposition A, approved on November 5, 2024, authorized $40 million for drainage facilities and improvements. - An $8.35 million FY2026 budget line for the Regional Drainage Program, which the budget codes as DR2202. This is a budgeted amount, not money already spent. - A $54 million FY2026 budget line for the Cypress Ditch Regional Flood Mitigation Project. The row is grant-funded and is also a budgeted amount, not spending.
A bond is repaid in a different way from a monthly fee, and the sources do not connect them. Treat the list as the drainage work on the City's books. A flat $6.50 a month is small beside numbers of that size, and the sources do not say how the fee and the project money fit together. To learn how the fee is used, ask the City.
Budget lines are not spending
A budget shows what the City plans and has permission to spend. It is not a receipt. The budget rows above are labeled as budgeted or appropriated for FY2026. Actual spending is reported later, in the City's audited financial report.
The same goes for the City's capital improvement plan. The City says only the current fiscal year's projects are part of the adopted budget, and that later years are planning guidance. So when you see a large number for a future year, it is a plan, not a promise.
How big the projects are
One large City drainage program is the Cypress Ditch program, which the City describes as a $110 million effort. Its scale and its funding are covered on the City's drainage projects page, listed in the sources below.
What this means for you
Look at your utility bill for the stormwater line and check that it matches the current rate sheet. For FY2026 that was $6.50 for a residential parcel. Do not assume a drainage project is paid directly from this fee unless a City source connects the two. If you want to know what the fee pays for, ask the City for the drainage utility's budget and its yearly report through the City's website. Ask separately about the bond projects, because the bond and the monthly fee are different sources of money.
Sources
- City of Bellaire: Stormwater Drainage Utility (https://www.bellairetx.gov/1921/Stormwater-Drainage-Utility)
- City of Bellaire: FY 2026 Utility Rates - Effective October 1, 2025 (https://www.bellairetx.gov/DocumentCenter/View/34539/FY-2026-Utility-Rates-PDF)
- City of Bellaire: Drainage Facilities and Improvement Projects (https://www.bellairetx.gov/1937/Drainage-Facilities-and-Improvement-Proj)
- City of Bellaire: FY2026 Adopted Budget (https://www.bellairetx.gov/DocumentCenter/View/34441/FY-2026-Adopted-Budget-PDF)
- City of Bellaire: Capital Improvement Plan (https://www.bellairetx.gov/1986/Capital-Improvement-Plan)